Steel HangerOvervi

Steel Buildings are fast becoming No.1 choice for construction to build metal warehouse, workshop or other industrial facilities. With today's advances in engineering and design, a Prefabricated Steel Building can be an attractive enhancement to commercial building or community complex.

Foundation

Prefab warehouse buildings in steelframe are constructed on the reinforced concrete foundations. Foundation: Design of concrete foundation with steel re-enforcement will be provided by FUUNZO.

After completion of the erection of all external walls, roof and suspended ceiling; leveling concrete (screed) must be prepared to install floor-covering materials.
Foundation and leveling works should be prepared on site.

steel Structure

Details of Steel Structure: Connected using galvanized bolts and nuts.

Design Loads: Floor load: 250 kg/m², Roof load: 100 kg/m², Wind load: 50 kg/m²
Earthquake Resistance – Level 8
Specification of Steel Works:
1. Material: Cold-rolled steel profile with hot dipped galvanized finishes
2. Manufacture of joint plate: Using steel plate welded. Hot-dip galvanized after adjustment.
3. Column connection: Using high tensile bolts to connect column with joint plates.
4. Roof beam connection: Using high tensile bolts to connect roof beam and joint plates.
5. Bracing: Bracing made with thread tapping and hot-dipped galvanizing finishes.

Wall and RoofCorrugated Metal Sheet: Corrugated pre-colored galvanized steel plate of 0.5mm. Or Insulated Sandwich Panel:Sandwich panel constructed by 2 layers of pre-painted steel plate and high-density insulation jointed by strong adhesive, under high compressed process to form solid panel.

The insulation material can be polystyrene, rock-wool or mineral wool.

Doors

Big Sliding Door or Roller Shutter Door is designed to meet logistic requirements.

Windows

PVC or Aluminum Window are used for ventilation